Draft Tube Erection
Erection of Spiral
Preparation for lowering of head cover assembly
Lowering of Stator in generator pit
Center marking of EOT hook for rotor lowering
Lowering of head cover
Heating of stator bottom bar for HV testing.
Final pressing of rimsheets of rotor is completed.
Erection of Spiral Assembly with the help HOT Crance manufactured by us. This preponed erection schedule by six months. Originally it was to be erected by EOT Crane which was operational only after complete height of column was achieved.